7 Dates to Track Until Coringa Permits Lift Serabi Gold’s Roughly 45,000-Ounce Cap

Serabi Gold's output is capped at about 45,000 ounces until Coringa's operating license is issued, which it expects in the first half of 2027. Here are 7 dates to track.

Project Overview

Serabi Gold (AIM: SRB | TSX: SBI | OTCQX: SRBIF) mines gold at 2 underground operations in Pará, Brazil, and treats the ore at 1 plant. Ore from the Coringa mine is pre-concentrated, meaning waste rock is removed before transport, and is processed at the Palito Complex, about 200 kilometers away by road. No stand-alone processing plant is planned at Coringa.

Coringa supplied 23,089 ounces (oz) of the 34,057 oz produced by Serabi in the first 9 months of 2026, at a year-to-date milled grade of 7.74 grams per tonne (g/t) gold, compared with 4.90 g/t at Palito. Third-quarter output was 11,008 oz, 9% below the same quarter of 2025, driven by lower-than-expected grades at Palito.

Coringa's operating license (LO) is expected in the first half of 2027, and updated resource estimates are expected in the second quarter of 2027, with a production guidance update due on November 27, 2026.

Source: Serabi Gold, Corporate Presentation, November 2026; Serabi Gold, Third-Quarter 2026 Production & Operational Highlights, October 21, 2026

1. November 27 Guidance Update

The next update to Serabi's production guidance is due on November 27, 2026, with its third-quarter financial results.

Permitting delays that affected the planned production ramp-up led Serabi to lower its 2026 expectations on October 21. Production is now expected to be at a level similar to 2025's 44,169 oz, compared with previous guidance of over 53,000 oz.

The approvals Serabi was waiting on would have allowed more Coringa material through the expanded Palito plant in the fourth quarter of 2026. They had not been received when the expectation was lowered.

2. September 30 Count: 85,602 Tonnes Against a 100,000-Tonne Allowance

Coringa's GUIA trial mining license allows up to 100,000 tonnes (t) of ore a year to be moved to Palito. By September 30, 2026, 85,602 t had been transported against the current annual allowance.

Over the 9 months to September 30, 2026, a total of 95,720 t of Coringa ore was transported to Palito. Material stockpiled at the surface and any additional ore mined at Coringa cannot be sent to Palito until that limit rises or the LO is issued. Consolidated production is capped at about 45,000 oz by the Coringa GUIA restrictions, and receipt of the LO removes that tonnage constraint.

3. January 29, 2027 GUIA Expiry

Coringa's current 3-year GUIA expires on January 29, 2027, and its continuation is Serabi's near-term licensing priority.

Discussions with the Agência Nacional de Mineração (ANM) regarding continuing operations under the GUIA are ongoing, supported by a legal petition in support of the request to continue. Speaking in July, Chief Executive Officer of Serabi Gold, Mike Hodgson, linked earlier GUIA extensions to understaffed public agencies in the north of Brazil:

"But there's nobody in these offices quite often, or they're so on demand they can't process the applications."

The ANM talks aim to keep Coringa operating until the LO is received.

4. First Half of 2027 Operating License

The LO is expected in the first half of 2027, the step that removes the processing restrictions at Coringa. The LO needs 2 approvals first, and both are progressing. Fundação Nacional dos Povos Indígenas (FUNAI) must give final approval to the Estudo de Componente Indígena, which both Indigenous groups have approved. Instituto Nacional de Colonização e Reforma Agrária (INCRA) must give final approvals at the state and federal levels for a change in land use that has been technically and legally agreed upon.

Secretaria de Estado de Meio Ambiente e Sustentabilidade do Pará (SEMAS) visited Coringa in September 2026. It then confirmed that Serabi may bypass the installation license stage, as Coringa will need neither a processing plant nor a tailings facility. Once the FUNAI and INCRA approvals are received, Serabi can apply directly for the LO, the final stage with SEMAS. The LO would then allow the ANM to issue the Portaria de Lavra, the mining concession that completes permitting at Coringa.

Hodgson described, before the guidance change, how Serabi explains that licensing position to investors:

"And so we have to kind of try to explain very complicated situations exactly where we are with our licensing. And it's almost like, look, it'll get done."

By October 21, 2026, the Estudo de Componente Indígena and the change-of-land-use agreements were nearing conclusion.

5. Fourth Quarter of 2026 Plant & Mining Changes

The fourth ball mill at Palito, installed in the fourth quarter of 2026, lifts plant throughput capacity to 900 tonnes per day (tpd) from 650 tpd.

Installation was completed on time and on budget; the mill was in final commissioning as of October 21, 2026, and annual processing throughput rises to 330,000 t in 2027.

At Coringa, the move from manual selective open stoping to mechanized sublevel stoping, a method that extracts ore in large blocks between underground levels, is on track for the fourth quarter of 2026. Mining is underway in the Serra, Serra South, Meio, and Galena zones, and full ramp-up is expected by the end of 2026.

6. November Drilling Finish & Second Quarter of 2027 Resource Update

Serabi's 2026 drilling concludes in November, and updated resource estimates are expected in the second quarter of 2027.

The US$9 million exploration program for 2026 includes 30,000 meters of diamond drilling, with brownfield drilling, meaning drilling near the existing mines, across both Palito and Coringa. The resource base stood at 1.4 million ounces (Moz) of gold as of the first quarter of 2026, and Serabi is targeting 1.7 to 2.0 Moz. Drilling in 2025 alone added about 400,000 oz, with the 2025 program adding about 300,000 oz at Coringa.

As of January 2026, Coringa carried measured and indicated resources of 304,000 oz at 8.9 g/t and inferred resources of 495,000 oz at 8.8 g/t. Palito had 427,000 oz at 9.3 g/t measured and indicated and 158,000 oz at 6.6 g/t inferred. The second-quarter 2027 estimates will show how far the 2026 drilling moves the 1.4 Moz base toward that target range.

7. Lower Capital Spending in 2027 

Capital spending is expected to be materially lower in 2027 following development at Serra South and Galena in 2026, and Serabi held US$63.2 million in cash and had no debt as of September 30, 2026.

Cash fell from US$65.7 million at June 30, 2026, as operating cash generation was offset by the US$5.1 million maiden dividend paid in July. A further US$3.4 million arrived on October 1, 2026, from September bullion sales, and a shareholder return policy is in place. The growth plan is fully funded. 

Key Takeaways for Investors

  • Coringa's GUIA trial mining license caps consolidated production at about 45,000 ounces until the limit rises or the operating license is issued.
  • The current GUIA expires on January 29, 2027, and discussions with the Agência Nacional de Mineração on continuing under it are ongoing.
  • The operating license is expected in the first half of 2027, after final approvals from the Fundação Nacional dos Povos Indígenas and the Instituto Nacional de Colonização e Reforma Agrária.
  • Updated resource estimates are expected in the second quarter of 2027, against a 1.4 million-ounce base and a 1.7 to 2.0 million-ounce target.
  • Serabi held US$63.2 million in cash and had no debt as of September 30, 2026, and capital spending is expected to be materially lower in 2027.

Bottom Line

Serabi Gold's production growth depends on licensing dates at Coringa. The November 27 guidance update comes first, followed by Coringa's GUIA expiry on January 29, 2027, and the LO that Serabi expects in the first half of 2027. Until either route lifts the tonnage limit, consolidated output is capped at about 45,000 oz, even with Palito's plant capacity at 900 tpd. The LO removes the Coringa processing restrictions; after permitting delays, the 2026 expectation is at levels similar to 2025's 44,169 oz. Resource estimates due in the second quarter of 2027 will then measure progress from 1.4 Moz toward the 1.7 to 2.0 Moz target. With US$63.2 million in cash, no debt, and lower capital spending expected in 2027, each of these dates can be tracked against a debt-free balance sheet.

Analyst's Notes

Institutional-grade mining analysis available for free. Access all of our "Analyst's Notes" series below.
View more

Subscribe to Our Channel

Subscribing to our YouTube channel, you'll be the first to hear about our exclusive interviews, and stay up-to-date with the latest news and insights.
Serabi Gold
Go to Company Profile
Recommended
Latest
No related articles

Stay Informed

Sign up for our FREE Monthly Newsletter, used by +45,000 investors