Vizsla Silver Orders About 85% of Panuco Process Plant Equipment & Targets First Silver in Second Half of 2028

Vizsla Silver reports Panuco engineering about 50% complete, about 85% of process plant equipment ordered, and first silver targeted for the second half of 2028.

  • M3 Engineering & Technology has completed approximately 50% of engineering for Panuco, and approximately 85% of the process plant equipment currently contemplated for the project has been ordered.
  • Vizsla Silver revised its targeted first silver production at Panuco to the second half of 2028, from the second half of 2027.
  • Aside from the schedule, the operating, capital, and economic parameters of the November 2025 Feasibility Study remain unchanged.
  • The company is working with Mexican federal authorities and third-party security advisors on a phased return to site.
  • Vizsla Silver has committed an initial US$5 million to the Vizsla Foundation, with plans to direct a percentage of future profits toward its work.

Company Overview

Vizsla Silver Corp. (TSX: VZLA | NYSE: VZLA | FRA: 0G3) is a Canadian development company advancing Panuco, its 100% owned silver-gold project in Sinaloa, Mexico. The company's November 2025 Feasibility Study (FS) outlines 17.4 million ounces of silver-equivalent annual production over an initial 9.4-year mine life, an after-tax net present value at a 5% discount rate (NPV5%) of US$1.8 billion, an internal rate of return (IRR) of 111%, and a 7-month payback period at US$35.50 per ounce of silver and US$3,100 per ounce of gold. Vizsla Silver is advancing mine development and district-scale exploration at Panuco to become a leading primary silver producer.

Engineering & Equipment Orders Advance Construction Readiness

Vizsla Silver is advancing Panuco, its wholly owned silver-gold project in Sinaloa, Mexico, with a focus on construction readiness. M3 Engineering & Technology has completed approximately 50% of engineering, and approximately 85% of the process plant equipment currently contemplated for the project has been ordered.

The company has awarded three development contracts covering engineering procurement and construction management, mine design, and equipment supply. The company will award the main mining contract in due course.

Vizsla Silver President and Chief Executive Officer Michael Konnert said the year's progress positions the company for the next phase:

"We have made significant progress advancing Panuco this year, achieving important milestones in engineering, procurement and development planning. We are well positioned to move into the next phase of development, with safety guiding our preparations for a phased return to site and first silver production now anticipated in the second half of 2028."

First Silver Targeted for the Second Half of 2028

Vizsla Silver revised its targeted first silver production at Panuco to the second half of 2028, from the second half of 2027 previously. The revised development schedule reflects current expectations for permitting, site readiness, and construction timing.

Project Parameters Remain in Place Except Timing

The company is not updating the operating, capital, or economic parameters from the November 2025 FS, other than the development timeline. The parameters are:

  • Processing capacity: 3,300 tonnes per day (tpd), increasing to 4,000 tpd in Year 4
  • Initial mine life: 9.4 years
  • Average annual production: 17.4 million silver equivalent ounces, and 20.1 million silver equivalent ounces on average in Years 1 to 5
  • Life-of-mine payable production: 94.7 million ounces of silver and 776,000 ounces of gold
  • Initial capital: US$238.7 million
  • Sustaining capital: US$287.3 million
  • Average cash costs: US$8.56 per silver equivalent ounce
  • Average all-in sustaining costs: US$10.61 per silver equivalent ounce
  • After-tax NPV5%: US$1.8 billion
  • After-tax IRR: 111%
  • After-tax payback period: 7 months

The economic results and the silver equivalent calculation use price assumptions of US$35.50 per ounce of silver and US$3,100 per ounce of gold. The revised schedule is not an updated economic study, and the FS economics have not been updated to reflect the revised schedule, potential cost escalation, financing costs, or other changes that may arise as the project advances. Dave D'Antonio, P.Eng., Senior Vice President of Technical Services for Vizsla Silver and a Qualified Person under NI 43-101, reviewed and approved the scientific and technical information in the company's update.

Security & Site Readiness

The company is planning employee and contractor safety guides for a return to site. Vizsla Silver is working with Mexican federal authorities and third-party security advisors to support additional security infrastructure, enhance overall security measures, and strengthen on-site support in preparation for a phased return.

These efforts build on an established approach that has included significant investment in security resources, third-party risk assessments, and adjustments to or suspension of activities in response to changing conditions. The timing and scope of any formal return to the project site will be informed by the company's assessment of security conditions and readiness.

Vizsla Foundation & Community Support

Since February 2026, Vizsla Silver has worked to establish the Vizsla Foundation as part of its long-term commitment to the people and communities of Sinaloa. The Foundation is intended to complement the direct assistance the company provides to families impacted by the tragic events of January 2026, and focuses on publicly available, multigenerational support and lasting opportunities for individuals and families across local communities. The company supports the Mexican authorities in their ongoing investigation.

Vizsla Silver has committed an initial US$5 million to the Foundation and plans to direct a percentage of future profits toward sustaining its work. Vizsla Silver is engaging with local communities to help shape the Foundation's priorities, including support for education, health, and economic development in the communities surrounding Panuco.

Konnert linked the company's commitment to the families with its outlook for the project:

"Our commitment to the families of our colleagues is enduring, as is our belief in Panuco's future and its potential to create lasting opportunities for the communities in Sinaloa and the people of Mexico."

Next Steps

  • Award of the main mining contract, to be made in due course.
  • A phased return to site, with timing and scope informed by the company's assessment of security conditions and readiness.
  • Further details on the Foundation's structure and programs, to be shared as plans progress and discussions with families continue.
  • A construction decision, which Vizsla Silver has not yet made. It will follow completion and review of detailed engineering, financing arrangements, and receipt of all required permits and approvals.

FAQs (AI-Generated)

When does Vizsla Silver now target first silver production at Panuco? +

Vizsla Silver targets first silver production at Panuco in the second half of 2028, revised from the second half of 2027.

How far along are engineering and equipment procurement at Panuco? +

Engineering is approximately 50% complete, and approximately 85% of the process plant equipment currently contemplated for the project has been ordered.

Did the revised schedule change the FS economics? +

Aside from the development timeline, the November 2025 FS parameters remain unchanged, including an after-tax NPV5% of US$1.8 billion and an after-tax IRR of 111%.

What is the status of the return to site at Panuco? +

Vizsla Silver is working with Mexican federal authorities and third-party security advisors to enhance security measures in preparation for a phased return to site.

What is the Vizsla Foundation? +

The Vizsla Foundation is intended to provide publicly available, multigenerational support and lasting opportunities across local communities, with an initial US$5 million commitment from Vizsla Silver.

Analyst's Notes

Institutional-grade mining analysis available for free. Access all of our "Analyst's Notes" series below.
View more

Subscribe to Our Channel

Subscribing to our YouTube channel, you'll be the first to hear about our exclusive interviews, and stay up-to-date with the latest news and insights.
Vizsla Silver Corp
Go to Company Profile
Recommended
Latest
No related articles

Stay Informed

Sign up for our FREE Monthly Newsletter, used by +45,000 investors