Kabanga's FID Risk Shifts to Financing as Lifezone Clears Resettlement

Lifezone advances Kabanga's resettlement, permitting and procurement, with Tanzania financing terms and lender diligence ahead of a first-quarter 2027 FID.
- An independent expert confirmed Kabanga's Resettlement Action Plan is in material alignment with International Finance Corporation Performance Standard 5, and the cap on consideration payable to BHP fell by $8 million as a result.
- The Special Mining License and all material permits for current activities are in place, while the 220-kilovolt power line agreements are under review and their tenders are scheduled for release in the fourth quarter of 2026.
- Lifezone has released 34 procurement packages to market and received 24 tenders, including the engineering, procurement and construction management, mining and bulk earthworks packages.
- October 2026 workshops confirmed the technical basis for a final investment decision, which the board is targeting for the first quarter of 2027.
- The Framework Agreement amendment and Joint Financial Model with the Government of Tanzania, the Orion Critical Mineral Consortium equity talks and lenders' final due diligence remain outstanding.
Lifezone Metals (NYSE: LZM) is targeting a final investment decision (FID) on the Kabanga Nickel Project in Tanzania in the first quarter of 2027. Two conditions stand ahead of the project financing: the amendment of the Framework Agreement with the Government of Tanzania, and agreement on the Joint Financial Model (JFM) that will define how economic benefits are shared between investors and the government. Lifezone has indicated that the financial investment decision (FID) could occur earlier with concerted effort, although the target remains subject to lenders' final due diligence and the conclusion of financing terms.
Equity is the second financing workstream. Negotiations with the Orion Critical Mineral Consortium (Orion CMC) on a significant strategic equity investment into Kabanga are at an advanced stage, and an investment would bring a strategic partner into the project ahead of FID. Orion CMC was created by Orion Resource Partners with the US International Development Finance Corporation and Abu Dhabi's L'IMAD.
On site, more of the work is done. Lifezone's third-quarter results record resettlement verified against lender standards, permits for current activities in place, procurement in evaluation and the first designs issued for construction. Kabanga's technical preparation for FID is well advanced; its financing is not yet cleared.
Resettlement Verified Against Lender Standards
On September 18, 2026, an independent expert's Determination Report confirmed that the Kabanga Resettlement Action Plan (RAP) had been prepared, developed and implemented in material alignment with the objectives of International Finance Corporation Performance Standard 5 (IFC PS5). The result also has a financial consequence: on October 7, 2026, Lifezone announced an $8 million reduction in the cap on consideration payable to BHP.
Chief Executive Officer Chris Showalter tied the verification to what lenders and investors will require of the project:
"This quarter we also received independent confirmation that the Kabanga Resettlement Action Plan is in material alignment with IFC Performance Standard 5, which reduced the cap on consideration payable to BHP by $8 million. This reflects our commitment to developing Kabanga to international standards, which is fundamental to securing project financing and to our partnerships with lenders and investors."
The compensation process is substantially advanced. Lifezone made 100% of cash compensation payments by the end of 2025, and 97% of project-affected households have signed compensation agreements and received payment, with the balance deposited into an escrow account for the remaining households.
Current Permits Secured as 220-Kilovolt Power Work Advances
The Special Mining License and all material permits needed for current activities are in place. Approvals received in the 9 months to September 30, 2026 include water use permits for new production boreholes and the updated Kabanga Environmental and Social Management Plan.
The 220-kilovolt transmission line is still in progress. TANESCO has received the environmental impact assessment for the line and is reviewing final drafts of the Implementation and Power Supply Agreements. Engineering, procurement and construction (EPC) tenders for the overhead line and associated substations are scheduled for release to market in the fourth quarter of 2026, and the corridor survey identified no risks to project execution.
Procurement Moves From Tender to Evaluation
Lifezone has released 34 packages to market and received 24 tenders, including the engineering, procurement and construction management, mining and bulk earthworks packages. The mining tender closed in September 2026 and is now under evaluation, with no contract awards disclosed.
A draft Project Controls Plan has been issued, and the team plans to implement the selected cost management platform in the fourth quarter of 2026. Market pricing and revalidation of key packages are underway to inform a preliminary update of the control budget estimate.
First Construction Designs Released as Site Preparation Advances
The North Boxcut and Waste Rock Dump designs have been issued for construction, and the Tembo Boxcut highwall and lateral support designs are complete. At the tailings storage facility, 12 of 15 planned geotechnical boreholes have been drilled.
October workshops finalized the integrated water balance and site layout and confirmed the technical basis for FID. Alternative water sources are being progressed for concentrator start-up and the initial fill of the tailings storage facility.
Site Mobilization Builds Ahead of Construction
The Mpingo camp is being upgraded to 350-person capacity, 20 prefabricated units have been installed at Pascal Pad, and 188 employees and contractors were directly engaged on the project at the end of September 2026. Kabanga has passed 3 million hours worked without a lost-time injury, with zero material health, safety, environmental or security incidents reported.

What Still Stands Between Kabanga & FID
The conditions left are financial and commercial. The project financing process is awaiting the Framework Agreement amendment, which includes the JFM. The Orion CMC negotiations are advanced but not concluded. The remaining $18.3 million under the Taurus Mining Finance senior secured bridge loan facility is contingent on the amendment being signed and is available for drawdown until November 29, 2026, following a 3-month extension agreed by Taurus. Lifezone held $22.2 million in cash at September 30, 2026.
The execution items are a separate category: evaluation of the mining tender, the preliminary update of the control budget estimate and procurement for the 220-kilovolt power line, with its EPC tenders scheduled for the fourth quarter of 2026. None of these appears among the financing conditions Lifezone has named.
With resettlement verified, current permits in place and the first designs issued for construction, Kabanga's technical case for FID has largely been assembled. The decision now depends on commercial agreement with the Government of Tanzania, the Orion CMC equity talks and lender approval.