Kabanga Advances 24 Tenders & Construction Designs While Lifezone Awaits Tanzania Terms

Lifezone's Kabanga nickel project has 24 tenders, construction designs and permits in place while Tanzania framework terms remain open ahead of a 2027 FID.
- Lifezone Metals' Board is targeting a final investment decision (FID) on the Kabanga Nickel Project in the first quarter of 2027, subject to lenders' due diligence and the conclusion of financing terms.
- Kabanga has received 24 tenders from 34 packages released to market, including the engineering, procurement and construction management, mining and bulk earthworks packages.
- North Boxcut and Waste Rock Dump designs have been issued for construction, and the integrated water balance and site layout were finalized at an October 2026 workshop.
- Cash resettlement compensation is fully paid, and an independent expert confirmed the Resettlement Action Plan is materially aligned with International Finance Corporation Performance Standard 5.
- The Orion Critical Mineral Consortium equity investment and the final $18.3 million of the bridge loan both await an amended Framework Agreement with Tanzania, alongside the lender and financing conditions on the FID.
What Has Happened
Lifezone Metals (NYSE: LZM) released its interim results for the 9 months to September 30, 2026, on October 29, 2026. The Board is targeting a final investment decision (FID) on the Kabanga Nickel Project in Tanzania during the first quarter of 2027. The company said the date could move later depending on lenders' final due diligence and the conclusion of financing terms.
The capital needed for that decision is still under negotiation. Talks with the Orion Critical Mineral Consortium (Orion CMC) on a strategic equity investment are at an advanced stage. They are awaiting an amendment to the Framework Agreement with the Government of Tanzania and a Joint Financial Model that sets how economic benefits are shared between investors and the government. The same amendment also conditions the final $18.3 million of Lifezone's bridge loan.
Over the same 9 months, Lifezone received 24 tenders on Kabanga's construction packages, issued North Boxcut and Waste Rock Dump designs for construction and completed cash resettlement compensation. Most of Kabanga's pre-construction workstreams are now at tender, design or completed status, while the agreement that releases the construction capital is not yet signed.

Procurement Has Reached the Tender Stage
Tanzania's Mining Commission has approved 59 Expressions of Interest for Kabanga. Lifezone has released 34 packages to market and received 24 tenders, including the engineering, procurement and construction management (EPCM), mining and bulk earthworks packages. The mining tender closed in September 2026, and evaluation has begun.
The tenders give the Board contractor pricing on the EPCM, mining and bulk earthworks packages before it takes the FID. The mining package is under evaluation, and bids on the EPCM and bulk earthworks scopes have been submitted.
Power Supply Agreements Remain Under TANESCO Review
Grid power supply is still at the pre-tender stage. Final drafts of the Implementation and Power Supply Agreements are under review by TANESCO. Engineering, procurement and construction tenders for the 220 kilovolts overhead power line and substations are scheduled for release to market in the fourth quarter of 2026.
The survey of the line's corridor identified no execution risks. The environmental and social impact assessment (ESIA) for the 220 kilovolts line, prepared to international standards, is on track for completion in the fourth quarter of 2026. Signed power agreements and released line tenders would bring power to the same tender stage as the mine packages.
Engineering & Site Work Moved to Construction Designs
Designs for the North Boxcut and the Waste Rock Dump have been issued for construction. At the tailings storage facility, 12 of 15 planned geotechnical boreholes have been drilled and the multichannel analysis of surface waves survey is complete. Interim site water balance results have been received. The integrated water balance and site layout were finalized at the October 2026 project workshop.
The owner's team is being built for execution at the same time. Organization designs, a Delegation of Authority and a governance framework were prepared for review at the October workshops. On site, the Mpingo camp is being upgraded to 350-person capacity and 20 prefabricated units have been installed at Pascal Pad. Kabanga had 188 employees and contractors at the end of September 2026.
Resettlement Compensation Paid & Material Permits in Place
Kabanga holds its Special Mining License and all material permits for its current activities. In a determination report dated September 18, 2026, an independent expert confirmed that the Resettlement Action Plan is in material alignment with International Finance Corporation Performance Standard 5 (IFC PS5).
The IFC PS5 determination also reduced the cap on consideration payable to BHP by $8 million for the period from July 18, 2025, to July 18, 2026, as Lifezone announced on October 7, 2026. Cash compensation payments are complete. 97% of project-affected households have signed and received payment, and the balance is held in escrow.
Kabanga recorded no material health, safety, environmental or security incidents and has worked more than 3 million hours without a lost-time injury.
What Is Still Open: Tanzania Terms & Financing
Lifezone’s funding comes from 4 sources with different conditions, and only the first 2 are in hand. Cash stood at $22.2 million on September 30, 2026, up from $20.1 million at December 31, 2025, after $24.8 million was invested in Kabanga over the 9 months. Lifezone also received $23.3 million in net proceeds from a $25 million registered direct offering completed on April 23, 2026. It had drawn $41.7 million of its $60 million senior secured bridge loan from Taurus Mining Finance, including $21.7 million during the 9 months
The other 2 sources are conditional. The remaining $18.3 million of the bridge loan depends on signing the Framework Agreement amendment, and Taurus has extended its availability by 3 months to November 29, 2026. Orion CMC was created by Orion Resource Partners, the US International Development Finance Corporation and L’IMAD, Abu Dhabi’s sovereign investment platform. Its strategic equity investment awaits the same amendment and the Joint Financial Model.
Chief Executive Officer Chris Showalter called the advanced Orion CMC negotiations the defining development. Signing the amendment would meet the condition on the bridge tranche, and the equity negotiations also await the Joint Financial Model. The FID still depends on lenders’ final due diligence and the conclusion of financing terms.
Broader Context: A Second First-Quarter 2027 Decision
At Lifezone's US platinum group metals recycling project, a pilot campaign on 1 ton of US-sourced autocatalyst material recovered more than 99% of the platinum and palladium, with rhodium recovery targeted above 95%. A feasibility study (FS) update and the project's FID are both now targeted for the first quarter of 2027. A preferred brownfield US site is under negotiation. A $25.6 million funding request to the US Department of Energy remains under review, although the August 2026 awards did not include Lifezone.
What to Watch Next
The first item to watch depends on Tanzania. Signing the Framework Agreement amendment and the Joint Financial Model would meet the condition on both the Orion CMC investment and the $18.3 million bridge tranche, which is available until November 29, 2026.
For the fourth quarter of 2026, Lifezone is targeting the release of the 220kV power line tenders and completion of the line's ESIA. The TANESCO Implementation and Power Supply Agreements are under review, with no stated completion date. The mining tender is under evaluation, and the EPCM and bulk earthworks tenders have also been received.
The Board is targeting the Kabanga FID for the first quarter of 2027. That date could move later depending on lenders' final due diligence and the conclusion of financing terms. The recycling project's FS update and FID are targeted for the same quarter.