Vizsla Silver's 7 Decision Points Between 50% Engineering & First Silver in 2028

Vizsla Silver's Panuco silver-gold project: 7 decision points on permits, security, site return, and the construction decision before first silver in 2028.
Where Panuco Stands Now
Vizsla Silver Corp. (TSX: VZLA | NYSE: VZLA | FRA: 0G3) is targeting first silver at its wholly owned Panuco silver-gold project in Mexico in the second half of 2028, moved from the second half of 2027. Approximately 50% of engineering is complete, and approximately 85% of the process plant equipment currently contemplated for the project is ordered.
Between those figures and first silver, 7 decision points remain: engineering and equipment, the mining contract, financing capacity, permitting, security infrastructure, the return to site and underground restart, and the construction decision.
1. Engineering Is About 50% Complete With About 85% of Plant Equipment Ordered
The company is advancing key development activities at Panuco with a focus on construction readiness, with M3 Engineering & Technology completing the engineering.
A decision to proceed with construction follows 3 conditions: completion and review of detailed engineering, financing arrangements, and receipt of all required permits and approvals. Completed detailed engineering is a prerequisite for that decision.
2. The Mining Contract Is the Remaining Development Award
The company has awarded 3 key development contracts, covering engineering, procurement and construction management (EPCM), mine design and equipment supply. M3 Engineering & Technology holds the EPCM contract, and the equipment supply contract covers the 8 major equipment packages for the mill.
The main mining contract will be awarded in due course and is the only award still outstanding. The EPCM and equipment supply awards give the company very high confidence in cost.
The November 2025 Feasibility Study (FS) sets initial capital at US$238.7 million. The company remains very confident in the FS numbers.
3. Financing Capacity of US$450 Million Equals 1.9x Initial Capital
Vizsla Silver holds US$450 million of financing capacity, equal to 1.9x initial capital. That total comprises US$411 million of cash and short-term investments as at July 31, 2026, US$29 million of equity holdings, and a US$10 million FIFOMI working capital facility.
The company describes the capacity as more than sufficient to begin construction upon receipt of key permits and a construction decision. The company does not need additional financing to fund the build, and the reduced funding risk allows it to focus on execution and advancing exploration.
4. Management Reports No Adverse Change to the Permitting Timeline
The company submitted the environmental impact assessment in February 2025, and key environmental permits are pending. Michael Konnert, Vizsla Silver's President and Chief Executive Officer, described the permitting outlook:
"There hasn't been any adverse changes to the permitting timeline as a result of this. In fact, what we're seeing is much broader, significant support for mines like this to be permitted and progressed."
Environmental impact assessments for several Mexican mining projects have been approved recently, and Konnert said Panuco's permit is likely to come in a reasonable time frame.
5. Security Planning Brings a Likely Military Installation & About US$10 Million of Spending
Employee and contractor safety continues to guide the company's planning for a return to site. Vizsla Silver is working with Mexican federal authorities and third-party security advisors to support additional security infrastructure, enhance overall security measures, and strengthen on-site support in preparation for a phased return.
A growing number of operators in Mexico are moving to more secure facilities, and the company's security plan follows that approach. The layout of some components around the site will change, with a likely military installation on the project, while the mill location, tailings, and underground mine will remain largely as described in the FS.
In Konnert's estimate, security investment of about US$10 million, plus US$5 million to US$10 million going forward, falls outside the FS items. At the FS prices of US$35.50 per ounce silver and US$3,100 per ounce gold, the economics cover those amounts.
6. A Phased Return to Site Reopens the Underground at the 460 Level
The company is preparing a phased return to site, with timing and scope informed by its assessment of security conditions and readiness, and is targeting a return towards the end of 2026. Konnert linked that timing to support from Mexican authorities:
"We're quite hopeful that we can do that towards the end of this year, and in large part that's due to the excellent cooperation and support that we've found in the government of Mexico and their Mexican military."
The company's underground plans include continuing the test mine beyond the permitted bulk sample, starting a stockpile of very high-grade Copala material above surface and developing multiple headings and underground infrastructure, to the extent this aligns with permits. The test mine provides access to the 460 level, the ore level at Copala.
The company has installed 2 drill bays underground at Copala. About 25 million ounces of inferred silver equivalent sit in the northern Copala-Cristiano intersection, within about 42 million ounces of inferred silver equivalent across the zone, with priority targets to convert mineralization in years 1 to 5. Drill plans from the underground bays continue through the Copala extension beneath the town of Copala.
7. A Construction Decision Sets the Path to First Silver in the Second Half of 2028
The company has not made a production decision for Panuco. Apart from the timeline, the company is not updating the FS operating, capital, or economic parameters.
The FS contemplates 3,300 tonnes per day of processing capacity, rising to 4,000 in year 4, over a 9.4-year mine life. Average annual production is 17.4 million ounces of silver equivalent, with 20.1 million ounces in years 1 to 5. Life-of-mine payable production is 94.7 million ounces of silver and 776,000 ounces of gold.
Sustaining capital is US$287.3 million, and all-in sustaining costs are US$10.61 per ounce of silver equivalent. Average cash costs are US$8.56 per ounce of silver equivalent. After-tax net present value at a 5% discount rate is US$1.8 billion, with an after-tax internal rate of return of 111% and a 7-month payback at FS prices.
Catalysts to Watch
- Completion of detailed engineering, currently approximately 50% complete
- Award of the main mining contract, which the company has said will come in due course
- Receipt of key environmental permits and all other required permits and approvals
- Start of the phased return to site, which the company is targeting towards the end of 2026
- Restart of the underground test mine and drilling from the 2 Copala drill bays after the return to site
- A construction decision following completion of detailed engineering, financing arrangements and receipt of all required permits and approvals
Bottom Line
Vizsla Silver has approximately 50% of engineering complete, approximately 85% of process plant equipment ordered, US$450 million of financing capacity, and 3 key development contracts awarded. The company is not updating the FS parameters, except for the timeline. The remaining steps to first silver in the second half of 2028 are the mining contract award, permits, the return to site, and the construction decision.