Erdene Targets 70,000 Ounces of Gold in 2027 as Bayan Khundii Grade Rises

Erdene targets 70,000 oz of gold in 2027 and 100,000 oz a year from Bayan Khundii in Mongolia, backed by Dark Horse, heap leach and debt repayment.
- Erdene Resource Development is tracking toward a feed grade of 3 g/t gold at its Bayan Khundii mine in Mongolia, which would put 2026 production in the 50,000 oz range.
- Erdene is targeting 70,000 oz of gold from Bayan Khundii in 2027 and is working to bring the high-grade Dark Horse satellite pit forward by mid-2027.
- The company has set out a route to 100,000 oz of gold a year at Bayan Khundii through a new heap leach facility and a 20% increase in plant throughput.
- Erdene's Bayan Khundii joint venture with Mongolian Mining Corporation repaid US$30 million of debt in the third quarter, has US$93 million left and is targeting full repayment in 2027.
- The preliminary economic assessment for Erdene's Zuun Mod molybdenum-copper project shows an after-tax NPV8% of US$745 million at base-case prices and US$2.0 billion at spot, and Erdene is seeking a development partner.
Erdene Resource Development Corp. (TSX:ERD) is moving the Bayan Khundii Gold Mine in southwestern Mongolia from ramp-up toward a stated goal of 100,000 ounces (oz) of gold a year. The mine poured first gold in September 2025 and sold 32,089 oz in the first nine months of 2026. Gold sales in the third quarter of 2026 reached 11,853 oz at a realized price of US$4,313/oz, generating US$51 million in revenue and C$9.6 million of net income for Erdene.
In an interview recorded on November 20, 2026, Erdene's leadership described a 2026 built on grade control, debt repayment and preparation for a satellite pit at Dark Horse. Beyond Bayan Khundii, Erdene holds 100% of the Zuun Mod molybdenum-copper project, where a preliminary economic assessment (PEA) delivered in October 2026 outlined a 34-year mine life.
Feed Grade and Production Target
Erdene is tracking toward a feed grade of 3 grams per tonne (g/t) gold, and holding that level through the fourth quarter would put 2026 production in the 50,000 oz range, according to the company. Third-quarter feed grade averaged 2.3 g/t, plant throughput rose 6% and gold recoveries held at 96%. Production was only slightly ahead of the second quarter as the operation widened the pit to reach the deeper, higher-grade Striker and Midfield zones. The mine is now in those zones and achieving the target grade, according to management.
The deposit's grade distribution explains why the ramp-up has been gradual. President and Chief Executive Officer of Erdene, Peter Akerley, described the challenge of feeding the mill:
"This deposit is characterized by very high grade and in some cases narrow zones. We probably have 80% of the value in 20% of the rock. So you can mine it as a whole and end up with two grams as an average grade, but it almost takes some surgical precision to get those very high-grade zones and get those into the mill so you can get that grade up."
Better blasting control, tighter dig lines, more geologists in the pit and high-precision GPS have lifted grade from 2 g/t toward 3 g/t. Akerley said improvement will come month by month into 2027, and the company sets a long-term grade target of 3.5 g/t.
Dark Horse Satellite Pit
Erdene is targeting 70,000 oz from Bayan Khundii in 2027, and the Dark Horse satellite pit is the lever. Akerley said Dark Horse holds about 50,000 oz of 7 g/t material at surface. The mine plan had scheduled that ore for 2028, and Erdene is working to bring it forward to mid-2027. If that happens, Akerley said blended grade could rise further and production could approach or exceed 70,000 oz. Erdene is targeting a final decision on Dark Horse timing in the first quarter of 2027.
Akerley put Bayan Khundii and Dark Horse together at about 450,000 oz in the 4.5 g/t range. A 3,000-meter (m) drill programme along the Dark Horse structures is underway, and Akerley said he believes it will add ounces.
Debt Paydown & the Joint Venture Cash Waterfall
Bayan Khundii is owned through Erdene Mongol LLC, a 50:50 subsidiary of Erdene and Mongolian Mining Corporation (MMC), a Hong Kong-listed coking coal producer. The split stays at 50:50 until the mine produces 400,000 oz of gold. Erdene's 5% net smelter return royalty applies to production above that threshold. Debt sits at the subsidiary level. It stood at US$93 million at the end of September, made up of a US$53 million shareholder loan from MMC and US$40 million from a commercial bank in Mongolia.
The joint venture repaid US$30 million in the third quarter, plans further repayments in the fourth quarter and is targeting full repayment in 2027, depending on the gold price. After that, cash not retained for exploration and sustaining capital goes to the two shareholders, under a board with equal representation that decides by unanimity. Akerley said Erdene can repatriate its share to Canada at a withholding tax of about 5%, then choose between buybacks and dividends.
Interview with Peter Akerley, President & CEO of Erdene Resource Development Corp.
West Striker, Ulaan & District Consolidation
The nearest exploration target lies immediately west of the Bayan Khundii pit at West Striker, where a 9,000 m programme is testing high-grade zones. Earlier drilling about 200 m west of the pit intersected 42 m of 7.27 g/t gold. Akerley said the area could host an additional 150,000 to 200,000 oz, and Erdene is targeting results through the first quarter of 2027.
West of that zone is ground Akerley called the triangle, held by a state-owned entity. Beyond it lies Erdene's Ulaan license, where the company has established a resource and, according to Akerley, received mining license approval in the days before the interview. Erdene plans to develop a mine plan to take to the government and to work with the holder of the triangle to develop a second deposit in the area, and those discussions are underway.
At Altan Nar, 16 kilometers (km) north of Bayan Khundii, a 30,000 m programme for 2027 awaits approval at December meetings in Mongolia.
Heap Leach & Plant Expansion: The Route to 100,000 Ounces
The plan for 100,000 oz a year adds steps to the 70,000 oz Bayan Khundii base. First is a heap leach facility for material below the carbon-in-pulp (CIP) cut-off. Dark Horse ore at 7 g/t and above goes to the CIP plant, and lower-grade material goes to the heap. Column leach tests at Blue Coast on Dark Horse oxide ore show recoveries in the mid-60% range, according to Akerley. He put lower-grade material at Dark Horse at close to 50,000 oz.
The Bayan Khundii low-grade stockpile is a second heap leach source, which Akerley said could ultimately hold about 150,000 oz at recoveries of 40% to 50% because the material is less oxidized. The Altan Nar oxide blanket is a third. Akerley said the heap leach could lift production toward 90,000 oz. Erdene is seeking approval from the joint venture board, then final studies, and is targeting construction in late 2027 or early 2028.
The final step is the CIP plant itself. It has no gravity circuit, and Akerley said relatively small capital could add about 20% more throughput. That would take output into the 100,000 oz range. A larger expansion to 150,000 to 200,000 oz a year depends on whether discovery and studies at Altan Nar and West Striker add another 1 million oz. Akerley placed that decision later, into 2028.
Zuun Mod: Partner-Led Development
The Zuun Mod PEA estimated an after-tax net present value at an 8% discount rate (NPV8%) of US$745 million and a 16.1% internal rate of return (IRR) at long-term prices of US$25.00 per pound (lb) molybdenum and US$5.00/lb copper. At spot prices of US$33.00/lb molybdenum and US$6.50/lb copper, the NPV8% rises to US$2.0 billion with a 27.8% IRR. Upfront capital is US$687 million, and payback falls in production year 6 in the base case.
A 4,500 m drill programme is testing near-surface areas to improve grade and continuity in the early years, where the strip ratio is high. Akerley said Erdene needs a partner to fund feasibility and development. Offtake and joint venture discussions are underway.
The Investment Thesis for Erdene Resource Development
- Bayan Khundii produced and sold 11,853 ounces of gold in the third quarter of 2026, and Erdene recorded C$9.6 million of net income for the period.
- Management is targeting 70,000 ounces in 2027, supported by bringing the higher-grade Dark Horse satellite pit forward by mid-2027.
- A heap leach facility and a plant throughput expansion form the route to the stated goal of 100,000 ounces a year, with heap leach construction targeted for late 2027 or early 2028.
- The joint venture repaid US$30 million of project debt in the third quarter, and full repayment of the remaining US$93 million is targeted in 2027, subject to the gold price.
- Erdene retains a 5% net smelter return royalty on Bayan Khundii production above 400,000 ounces, and holds 100% of the Zuun Mod molybdenum-copper project.
- Monitor West Striker drill results through the first quarter of 2027, the Dark Horse timing decision, and the December approval of the 2027 Altan Nar drill programme.
Erdene combines a cash-generating, high-grade gold mine with a growth plan that depends on grade delivery, joint venture approvals and continued exploration success.
Macro Thematic Analysis
Gold sets Erdene's cash flow. Bayan Khundii realized US$4,313/oz in the third quarter against cash costs of US$1,742/oz and all-in sustaining costs of US$1,848/oz. Gold has pulled back in recent weeks and Akerley cited diesel prices as a drag on costs, yet third-quarter margins still funded a US$30 million debt repayment.
Molybdenum sets the long-dated option. Akerley said the price remains above US$32/lb, supported by a supply deficit in Asia. The company attributes demand growth to specialty steel for defense and high-technology uses and to China's shift toward higher-quality steel, while Chinese molybdenum mines approach end of life.
Akerley described the location argument for Zuun Mod:
"What really sets Zuun Mod apart from other molybdenum projects globally is its location relative to China. In an area that was once considered remote and infrastructurally challenged, we now have road and rail and power all coming in. So infrastructure has become an advantage as opposed to a disadvantage, and here we are next to the largest consumer of molybdenum who can't find enough of it."
The project is about 280 km from the railhead on the Mongolia-China border. Akerley said a 34-year mine life on a deposit open in all directions suits a major Asian company seeking multi-decade supply. Price assumptions alone separate the US$745 million base case from the US$2.0 billion spot case.
TL;DR:
Erdene Resource Development is targeting 70,000 ounces (oz) of gold from its Bayan Khundii mine in Mongolia in 2027 and 100,000 oz a year within the next couple of years. Third-quarter 2026 sales of 11,853 oz at US$4,313/oz delivered C$9.6 million of net income. The joint venture with Mongolian Mining Corporation repaid US$30 million of debt, leaving US$93 million, and is targeting full repayment in 2027. The route to higher output runs through four steps: grade rising from 2 toward 3 grams per tonne, an earlier start at the high-grade Dark Horse pit, a heap leach and a plant expansion. The 100%-owned Zuun Mod molybdenum-copper project adds a 34-year option that needs a partner.